Arizona utility asks regulators to rethink gas plant expansion

Dive Temporary:

  • Salt River Project on Monday requested Arizona regulators to rethink their April rejection of a proposed 820-MW expansion on the gas-fired Coolidge Technology Dwelling, citing “legal and steady errors” in the dedication. With out the brand new capability, the utility says machine reliability might perhaps perchance aggravate within two years.
  • The Arizona Corporation Rate concluded there used to be insufficient proof to approve the mission, and that the expansion would injure the nearby, traditionally-Sunless community of Randolph. Regulators denied the mission in a 4-1 vote.
  • SRP’s enchantment proposes new mitigation measures for the community, in conjunction with dual carriageway paving, dwelling repairs and efficiency measures. However advocates whisper the utility has unruffled failed to deal with questions of designate and resource mix, and the ACC need to unruffled stand by its new dedication.

Dive Insight:

SRP faces a “excessive possibility of insufficient resources major to meet buyer count on in 2024” except Arizona regulators reverse their denial of the Coolidge expansion, the utility acknowledged in a bid issued Friday.

The rejection will additionally “undermine SRP’s skill to combine extra renewable resources, because the utility will lack vital rapid-originate, flexible generation in times of peak count on,” it acknowledged.

SRP has plans to diminish carbon intensity bigger than 65% by 2035 and 90% by 2050, relative to 2005 ranges. “On the choice hand, in this day’s unstable market, which is challenged by provide chain shortages and delays, SRP need to produce confirmed, legit solutions to manufacture obvious a neat vitality future,” the utility acknowledged in its request for rehearing.

However opponents of the gas plant expansion whisper the utility did no longer use into consideration other resource alternate choices or provide diagnosis of possible vitality bill impacts for possibilities.

“SRP’s rehearing request does tiny to deal with the explanations the ACC rejected the gas plant expansion proposal in the first region, in conjunction with providing regulators with ample knowledge to test if increasing Coolidge can be an economically sound option for Arizona ratepayers,” Developed Energy Economic system Protection Necessary Shelby Stults acknowledged in a bid.

SRP says it has proposed an additional $18 million in community make stronger, in conjunction with extra dual carriageway paving, dwelling repairs and vitality efficiency enhancements, and as much as $2 million for a brand new community heart. However beyond higher community concessions, “SRP’s notion unruffled falls short,” Stults acknowledged.

According SRP’s rehearing request, Arizona regulators relied on unsuitable legal and steady conclusions of their dedication, incorrectly deemed the mission application incomplete, and wouldn’t agree with made conclusions regarding anticipated environmental impacts on Randolph.

“The listing does no longer point to any field cloth adverse environmental affect and SRP dedicated to providing acceptable air emission, noise, and visibility mitigation actions,” the utility acknowledged.

SRP additionally argued the denial used to be arbitrary, unreasonable and unlawful for the reason that ACC “has no jurisdiction over SRP’s resource planning route of.”

The ACC does no longer lend a hand watch over SRP charges, however on story of the scale of the proposed gas plant expansion, the price’s approval used to be required. The utility wants to set up 16 new gas generators however confronted pushback from consumer advocates and local residents over charges of vitality racism, environmental injustice and the dearth of a aggressive bidding route of for the virtually $1 billion mission.

The need for imprint new generation resources is subtle by the U.S. Department of Commerce’s investigation into possible solar tariff circumvention, SRP effectively-known in its request.

“Solar panel provide chains had been significantly disrupted, and all of the solar initiatives that SRP has below contract to originate operation in 2023 and 2024 are at possibility of famous delays and price increases,” the utility acknowledged. The provision chain problems are expected to continue “for the foreseeable future.”

SRP acknowledged it has 1,350 MW of solar and battery storage initiatives shriveled to be on-line by summer season 2024 “and is depending on these initiatives — besides to the Coolidge Expansion Project — to manufacture obvious resource adequacy for its possibilities.”

Read More