HS2 stays on budget… but which budget?

Chalfont St Peter vent shaft for the Chiltern tunnels

The latest budget for HS2 Fragment One (London-Birmingham) stands at £44.6bn. Of this, £14.9bn has been spent, with a extra £800m for land and property provisions. £12.7bn has been gotten smaller but now not yet in point of fact spent.

That £44.6bn budget figure is now not what the federal government orHS2 Ltd expects it to cost. It ought to ‘most effective’ cost £34.7bn – in conjunction with programs and trains apart from constructing. On the other hand £5.6bn has been added for contingencies to give HS2 Ltd a aim cost of £40.3bn.

To this £40.3bn aim cost the federal government has added one other £4.3bn contingencies of its believe, to arrive at a ‘budget’ of £44.6bn.

So were HS2 Fragment One to attain in at £42.0bn, the federal government (and the patron organisations) would be ready to crow that the project had attain in £2.6bn below budget – even supposing it would possibly maybe maybe well enjoy in point of fact cost £7.3bn extra than it must enjoy.

These £9.9bn contingencies are there for a reason.

HS2 Ltd has to this level drawn £1.3bn of its £5.6bn delegated contingency, in conjunction with £500m previously six months, that manner £4.3bn stays.

HS2 Ltd is reporting £1.7bn of “seemingly future cost pressures that are for the time being presenting at some level of the programme”. These encompass an estimate of £800m for seemingly additional most fundamental works civils charges stemming from additional make charges and slower than anticipated growth in some areas. That figure has risen from £200m six months ago.

There is furthermore a “stress” of £400m on the associated payment estimate for the HS2 Euston field and £200m against HS2 Ltd’s budget for adjustments to Community Rail infrastructure at Euston and Aged Oak Current that are required to facilitate the new HS2 stations.

On Covid-19 charges, HS2 Ltd’s review of the likely financial influence of the pandemic on turning in Fragment One is estimated at some level of the variety of £400m to £700m.

Ongoing protester process, in conjunction with the elimination of camps and boom-linked delays to the programme, has cost merely about £122m to this level.

The minister’s plump story shall be read at www.gov.uk