BankingBanking & FinanceBusinessBusiness & EconomyBusiness Line

Pakistan may per chance per chance additionally face $18bn penalty if it doesn’t complete Iran gasoline challenge

Considerations had been raised by Pakistan’s Public Accounts Committee (PAC) on Wednesday over the fee of $18 billion in penalty if the country does no longer plug forward with the Iran-Pakistan Gas Pipeline challenge,  DAWN reported.

As quoted, PAC Chairman Noor Alam Khan stated, “The US must restful pay the penalty if it does no longer approve of Pakistan and Iran going forward with the gasoline pipeline challenge.”

“The USA must decide up away with double requirements — being lenient with India in assembly its vitality wants while punishing Pakistan for the identical,” Khan added.

As per the record, the commentary came after Pakistan’s Ministry of International Affairs (MoFA) wrote a letter to PAC to present that a assembly with the US ambassador would be arranged after his return from Washington.

As quoted by DAWN, the ministry stated: “In peep of the huge significance of the Iran-Pakistan (IP) gasoline pipeline challenge within the emerging regional inform, this ministry has been exploring all that you just may well perchance per chance additionally imagine alternatives, including discontinuance engagements and essential exchanges with connected occasions, including Iran and the US.”

“On this regard, a technical group of workers from the petroleum division visited Tehran in January to focus on suggestions and ability to proceed with the IP gasoline challenge. The High Minister’s Space of enterprise has held inter-ministerial conferences of all stakeholders and agreed on an motion idea to proceed on the IP gasoline pipeline challenge,” it added.

Whereas responding to a question concerning the aquire of petroleum products from Russia, the international ministry stated that an agreement has been made with Moscow to aquire a test cargo of coarse oil, which may near in Pakistan quickly.

The ministry stated, “Pakistan was once committed to the Pak Circulate Pipeline challenge. The 2 facets are negotiating outstanding disorders.”

Iran-Pakistan Gas Pipeline Mission

The challenge is an below-building pipeline to utter pure gasoline from Iran to Pakistan. It is far being constructed to retain pure gasoline from Iran’s South Pars enviornment to Baluchistan and Sindh provinces in Pakistan.

Reports net talked about that the pipeline will allow Pakistan to originate receiving 750 million cubic toes of gasoline from Iran each day.

The challenge was once speculated to be finished by December 2014, with operations origin on January 1, 2015, however there were big delays.

Earlier this 365 days, Tehran urged a visiting Pakistani legitimate delegation that the US sanctions on Iran are illegal. It additionally stated that Pakistan must restful invent the gasoline pipeline in its territory by February-March 2024.

(With inputs from companies)

WATCH WION LIVE HERE

That you just may well now write for wionews.com and be a part of the community. Half your reports and opinions with us here.

Content Protection by DMCA.com